It has been a while since we last posted a #sitevisitgodfrey post and wanted to keep you all up on the progress. We have been busy on the property replicating the work completed on the lower floors in the building interior with framing, plumbing, etc… for the guest room floors. We now have all the guest room floors from 5 through 16 being worked on.
As you have noticed if you walked by the hotel that the outer paneling of the building has been going up incredibly fast. We now have windows on the guest room floors and windows on the east and west walls being installed. The building on the North/South sides will have a total of 307 operable windows! The West side of the building facing LaSalle will have windows on the entire side from the ground floor up to 16. We have started the process on floor 5 to enclose the guest room floors first.
A big part of a hotel building project as I have stated is working in phases and now most phases are in full motion. Check out most of the update pictures below and enjoy some unique shots of the building.
South Side Of Building:

Scaffolding to install under section paneling on building

Paneling being installed on South Side Upper Section

Under paneling installed and windows in guest rooms. Yes, our guest room windows do open.

Building paneling delivery waiting to be installed on the 4th Floor Roofscape.
A View From The Top:

Steel Installation for HVAC Equipment

South Facing View with Steel from Rooftop

North East View from Rooftop

Beautiful View of the City Skyline South Facing

16 Floors Straight Down looking at N. LaSalle

16 Floors Straight Down looking at W. Huron St.
On The Inside:

West Facing Truss Joints

Truss Joints Facing South West

Service Elevator Cut-Out 16 Floors Down

Service Elevator Cut-Out

Two Guest Room Windows

Now that is a lot of wiring

HVAC Fan, very industrial.

Who knew they put that putty on the back of every electrical outlet

Glass Wall Curtain Windows Facing East towards the Hotel Felix
The Glass Curtain Facing West:

Windows Delivered Sitting In Crate

These are not your typical windows…

The two man crew uses scaffolding lowered down and a huge 3 suction window holder to position each piece

Floor 5-7 complete, when complete this side of the building will have an amazing look.
ENJOY YOUR MEMORIAL WEEKEND!