Big Changes #sitevisitgodfrey

It has been a while since we last posted a #sitevisitgodfrey post and wanted to keep you all up on the progress.  We have been busy on the property replicating the work completed on the lower floors in the building interior with framing, plumbing, etc… for the guest room floors.  We now have all the guest room floors from 5 through 16 being worked on.

As you have noticed if you walked by the hotel that the outer paneling of the building has been going up incredibly fast.  We now have windows on the guest room floors and windows on the east and west walls being installed.  The building on the North/South sides will have a total of 307 operable windows!  The West side of the building facing LaSalle will have windows on the entire side from the ground floor up to 16. We have started the process on floor 5 to enclose the guest room floors first.

A big part of a hotel building project as I have stated is working in phases and now most phases are in full motion.  Check out most of the update pictures below and enjoy some unique shots of the building.

South Side Of Building:

South Scaffolding Godfrey Hotel Chicago
 Scaffolding to install under section paneling on building

South Panels Looking Up Godfrey Hotel Chicago

Paneling being installed on South Side Upper Section

Guest Room Windows Open Godfrey Hotel Chicago
 Under paneling installed and windows in guest rooms.  Yes, our guest room windows do open.

Building Panels Godfrey Hotel Chicago
  Building paneling delivery waiting to be installed on the 4th Floor Roofscape.

A View From The Top:

Roof HVAC 2 Godfrey Hotel Chicago

Steel Installation for HVAC Equipment

Roof HVAC 3 Godfrey Hotel Chicago

South Facing View with Steel from Rooftop

Roof HVAC Godfrey Hotel Chicago

North East View from Rooftop

Beautiful South View Godfrey Hotel Chicago

Beautiful View of the City Skyline South Facing

16 Floors Down LaSalle Godfrey Hotel Chicago
16 Floors Straight Down looking at N. LaSalle

16 Floors Huron St Godfrey Hotel Chicago

16 Floors Straight Down looking at W. Huron St.

On The Inside:

West View with Truss Godfrey Hotel Chicago

West Facing Truss Joints

Truss Joint Godfrey Hotel Chicago

Truss Joints Facing South West

Service Elevator 16 Floors Down Godfrey Hotel Chicago

Service Elevator Cut-Out 16 Floors Down

Service Elevator Cutout Godfrey Hotel Chicago

Service Elevator Cut-Out

Guest Room Window Godfrey Hotel Chicago

Two Guest Room Windows

Floor Wiring Godfrey Hotel Chicago

Now that is a lot of wiring

HVAC Fan Godfrey Hotel Chicago

HVAC Fan, very industrial.

Electrical Outlet Putty Godfrey Hotel Chicago

Who knew they put that putty on the back of every electrical outlet

East Facing Glass Curtian Godfrey Hotel Chicago

Glass Wall Curtain Windows Facing East towards the Hotel Felix

The Glass Curtain Facing West:

NMS_0294

Windows Delivered Sitting In Crate

West Facing Glass Window Size Godfrey Hotel Chicago

These are not your typical windows…

West Glass Curtain Installation Godfrey Hotel Chicago

The two man crew uses scaffolding lowered down and a huge 3 suction window holder to position each piece

West Glass Curtain Wall Installation Godfrey Hotel Chicago

Floor 5-7 complete, when complete this side of the building will have an amazing look.

ENJOY YOUR MEMORIAL WEEKEND!

 

Taking A Look Back

We found a great photo of the River North Neighborhood we wanted to share.  It is only fitting since we are changing the skyline in the area that we take moment and look back at how River North used to look.  How about we take a look way back, pre-1950 way back.  Do you think you can tell where our hotel will be located?

Photo credit and found on Skyscraper Forum – Historic Chicago Thread: http://goo.gl/mx01p

Historic River North Chicago

A Good #sitevisitfriday

On Good Friday last week we went to the site to see an update on the new hotel.  We can say it is definitely coming along and it was a beautiful day to see the city from our floors.  The process of development of the hotel has to happen in phases, with so many different teams working together it is important they all coordinate on each process.  Development and construction meetings take place weekly with updates to the team.  Stay tuned for an update on the front of the building with the outside skin being applied.

lone pipe

Now that the fire proofing is complete on the building a lone pipe sits where the hose was connected to the sprayer to deliver the product.

1st Floor Lobby

The lobby shot as of today.  This is going to be a great before shot for a before and after post.

Remember the Salamander Heaters? Here is one running up close, talk about some heat.

Door Way Frames

The door way to no where right now but eventually it will be the door ways to your awesome experience in our hotel.

Outside Corner Panels

Outside corner panels for the front of the building.

Measurements

Corner panels being custom fit for the building, it is all about the measurements.

4th Floor Before

4th floor of the hotel where our meeting space and 4th floor urban roofscape will be at.

Bathroom Wall

Guestroom bathroom framing.

Shower Valve Installed

All those valves from a previous post you saw have been installed, here is the final product for the shower valves.

At The End Of The Copper Tunnel

Copper Piping – The Light At The End Of The Tunnel

Oh The Lead

The lead that is used to seal the major plumbing in the building.  The team melts this and it is poured onto the pipes.

Scaffolding Back Wall

The 4th floor outside deck area with scaffolding installed to begin window installation.

Do Not Cut

Do Not Cut – Painted lines display where the support beams have been placed into one of the floors.

Cold Valves

An ice cold frosted valve from the oxygen tanks at the site for the workers equipment that utilizes them.